We use cookies to offer the best possible user experience on our website. We also use third-party cookies, to deliver personalised advertisement messages. By using our website you agree, that cookies can be saved on your device. Further information on the cookies used and on how to disable them can be found here.
 
 
 
 
 

Garibaldi Primary School, Soliera (MO)

Garibaldi Primary School, Soliera (MO)
 
Garibaldi Primary School, Soliera (MO)
 
Garibaldi Primary School, Soliera (MO)
 
Garibaldi Primary School, Soliera (MO)
 
Garibaldi Primary School, Soliera (MO)
 
 
The Project
In May the earth moved.
In September the new school was ready for occupation!
The detailed design took just eleven calendar days.
Actual construction lasted 43 days
On 30th September 2012 the work was successfully concluded.

The school offers 14 classrooms for the current 336 children, a library a multipurpose room, a dining hall and the necessary sanitary facilities. Construction was directed on ecological, pedagogical and functional lines right from the project phase. The use of post and beam construction and the selection of materials consistently continued these criteria into the construction phase. The principal considerations were energy efficiency, seismic safety, flexible use of space and pleasant acoustic features.
Comfort from above, however, was also important - a flat roof package with timber ceilings as a load-bearing structure guarantees a high phase shift. The school attains Energy Efficiency Class A (corresponds to energy consumption of below 30 kWh/m²a) and the spacious photovoltaic system on the roof alone brings energy savings of some 30 to 40%.
Technical data and information
Client: Regione Emilia Romagna, Commissario Delegato emergenza sisma
Cubage: 4.158 m³
Architecture: ViTre Studio S.r.l., Arch. Gianluca Perottoni
Construction period: August 2012 - September 2012
 
Construction period: 1 Month
Please select the month for more info
2012
January
February
March
April
May
June
July
August
September
October
November
December
 
 
 
Back to list
 
 
 
 
 
 
© 2017 Rubner Objektbau GmbH | VAT No. 02223110210 | Imprint | Cookies | Sitemap | Leg. Decree 231/2001 | Privacy Go to top
 
 
Newsletter RUBNER