We use cookies to offer the best possible user experience on our website. We also use third-party cookies, to deliver personalised advertisement messages. By using our website you agree, that cookies can be saved on your device. Further information on the cookies used and on how to disable them can be found here.
 
 
 

SITE - WORK

The electrical installation and the preparation of special "small-dose" systems:

• the inside of each Cluster has at least:
o a medium to low voltage transformer cabinet
o a main distribution board to power the pavilions and all service rooms for the area

• the electrical wiring in the prearranged pipes below the foundations branch off from the technical rooms to the electrical switchboards for the area

• inside the pavilions:
o power distribution is carried out with visible rigid pipes in PVC
o control and user points have been installed in the spots indicated by the executive plans

• creation of the data transmission system, including of the category 5e data-transmission points in the spots indicated by the executive plan: provided in modular rack panels

• pipe laying for the CCTV, anti-intrusion and sound diffusion systems.